Overview
Concrete Commitments are specialized agreements for managing concrete pours on construction projects. Unlike standard material commitments, concrete commitments include:- Mix design specifications
- Pour scheduling and coordination
- Delivery location management
- Vendor communication for just-in-time delivery
Key Concepts
Pour
A Pour is a scheduled concrete placement event. Each pour specifies:- Location – Where on the job site
- Mix Design – The concrete specification
- Volume – Cubic yards required
- Date/Time – When the pour is scheduled
Mix Design
The specification for the concrete, including:- Strength (PSI)
- Slump
- Aggregate size
- Admixtures
- Special requirements (fiber, color, etc.)
Creating a Concrete Commitment
Adding Mix Designs
Define the mix designs available under this commitment:Enter Mix Details
- Name – Descriptive name (e.g., “4000 PSI Slab Mix”)
- Strength – PSI rating
- Slump – Consistency specification
- Price per CY – Committed price per cubic yard
Scheduling Pours
Creating a Pour
Enter Pour Details
- Location – Where on site (e.g., “Building A, Level 2 Slab”)
- Volume – Estimated cubic yards
- Date – Scheduled pour date
- Start Time – When trucks should arrive
Pour Calendar
View all scheduled pours in calendar format:- Daily View – See all pours for a specific day
- Weekly View – Plan the week’s concrete work
- Monthly View – Long-term pour planning
Pour States
| State | Description |
|---|---|
| Scheduled | Pour planned and on calendar |
| Confirmed | Vendor has confirmed the date |
| In Progress | Pour is happening |
| Completed | Pour finished successfully |
| Cancelled | Pour cancelled |
| Rescheduled | Moved to a new date |
Coordinating with Vendors
Sending Pour Requests
Vendor Confirmation
When the vendor confirms:- Pour status updates to Confirmed
- You receive notification of confirmation
- Any changes from vendor are noted
Day-of-Pour Management
Pre-Pour Checklist
Before the pour begins:Confirm vendor has the pour on schedule
Verify mix design is correct
Ensure site is ready to receive concrete
Confirm equipment and crew are in place
During the Pour
Track actual delivery:- Record truck arrivals and ticket numbers
- Note actual volumes delivered
- Track any issues or delays
- Capture delivery ticket photos
Completing the Pour
After the pour:Tracking Commitment Usage
Commitment Progress
Monitor how much of your commitment has been used:- Total Committed CY – Cubic yards in the agreement
- Poured CY – What’s been placed
- Scheduled CY – Upcoming pours
- Remaining CY – Available for future pours
Cost Tracking
Track spend against commitment:- Actual costs per pour
- Comparison to committed pricing
- Any additional charges (pumping, overtime, etc.)
Handling Changes
Rescheduling Pours
To move a pour to a different date:- Open the pour
- Click Reschedule
- Select new date and time
- Notify vendor of change
Adjusting Volumes
If pour requirements change:- Open the pour
- Update the estimated volume
- Notify vendor if significant change
- Track actual vs. estimated after pour
Weather Delays
For weather-related issues:- Monitor weather forecasts
- Communicate early with vendor
- Reschedule proactively
- Document weather-related changes
Reports
Pour History
View all pours for a project:- Dates and locations
- Volumes placed
- Mix designs used
- Cost summaries
Commitment Utilization
Track commitment usage:- Percentage of commitment used
- Remaining capacity
- Cost comparison
Best Practices
Confirm Early
Get vendor confirmation at least 48 hours before pour.
Track Weather
Monitor forecasts and have backup plans.
Capture Tickets
Photograph delivery tickets immediately.
Communicate Changes
Notify vendors promptly of any schedule changes.